Calvert Street Reconstruction
The City of Dallas, Public Work and Transportation Department Calvert Street Reconstruction project scope included the reconstruction of pavement, sidewalks, driveways, drainage, and water line for 1,400 L.F. of industrial street.
Dikita performed design services for approximately 1,400 linear feet of street reconstruction, including paving, drainage, sidewalks, driveways, wastewater and water main improvements for Calvert Street. The storm drainage improvements included 21” to 36” reinforced concrete pipe, two 5-foot manholes and six 10-foot inlets.
Owner:
City of Dallas
Location:
Dallas, TX
Services Provided:
Engineering Services
Project Cost:
$830,000
Completion Date:
2005
Contracted Responsibility:
Prime